Conveyor carriers and structure in a manufacturing hall

Guide · 4 min read

Conveyor Factory Acceptance Test (FAT): Checklist and Best Practice

A factory acceptance test catches problems while they are cheap to fix. Here is what to test and check before your conveyor leaves the factory.

A factory acceptance test (FAT) is a structured check of equipment at the manufacturer's factory, before shipment. For overhead conveyors, it typically covers drives, switches, stops, lifts, carriers and control panels that can be assembled and run in the workshop.

FAT vs SAT

Factory and site acceptance tests
Factory acceptance test (FAT)Site acceptance test (SAT)
WhereManufacturer's factoryYour plant
WhenBefore shipmentAfter installation and commissioning
WhatFunction of key assemblies and panelsWhole line at the agreed output
GoalFind defects before shippingConfirm the line meets the contract

Prepare the FAT

  • Agree a written test procedure with pass criteria before the test
  • Agree which assemblies are pre-assembled and run
  • Prepare test products or dummies with the right weight
  • Decide who attends, in person or by video
  • Prepare a punch list template for open points

What to test

FAT checklist for overhead conveyors
ItemChecks
DrivesSmooth running, direction, current draw, overload protection
SwitchesCorrect switching in both directions, end-position sensors
StopsHolding and release, sensor feedback, accumulation behaviour
Lifts and drop sectionsTravel, positioning, brakes and safety catches
CarriersDimensions, locating points, fit with test product, welds
Control panelsWiring check, I/O test, PLC program functions, HMI screens
SafetyEmergency stops, interlocks and guards
DocumentsDrawings, wiring diagrams, manuals, spare parts list, certificates

Video FAT

When travel is not practical, a live video FAT works well if it is prepared: a written test plan, a camera operator who follows instructions, close-ups of measurements and HMI screens, and a recording for the project file.

After the FAT

  • Sign the FAT report with results and open points
  • Agree dates for closing each punch list item
  • Approve packing only when critical points are closed
  • Link the shipment payment milestone to the signed FAT report

Then the SAT

The site acceptance test usually includes running the line at the agreed output for an agreed period. Define this in the contract. See our installation guide for the steps before SAT.

Customers are welcome to inspect their equipment at HITREE before shipment; see factory and quality or contact us.

Sample FAT test sheet

Example factory acceptance test entries
TestMethodPass criterion
Switch functionCycle each switch 20 times in both directionsNo missed end-position signal
Stop functionHold and release a loaded carrier 20 timesCarrier disengages and re-engages every time
LiftRaise and lower with rated loadPositions within tolerance; brake holds
Emergency stopActivate each E-stopAll motion stops; reset works as specified
HMICheck each screen and alarmMatches the approved specification

Example only; your test procedure should match the contract and the equipment.

Common FAT mistakes

  • No agreed pass criteria before the test
  • Testing without load, so issues appear only on site
  • Skipping documentation checks
  • Signing without a dated punch list

A thorough conveyor factory acceptance test takes a little extra time before shipping and can save weeks on site.

FAQ

Frequently Asked Questions

What is a factory acceptance test for a conveyor?

A structured test at the manufacturer's factory, before shipment, of key conveyor assemblies and control panels against agreed criteria.

Can a FAT be done by video?

Yes. With a written test plan and a well-prepared camera operator, a live video FAT is a practical alternative to travel.

What is the difference between FAT and SAT?

FAT checks equipment at the factory before shipping; SAT checks the installed line at your plant against the contract output.